Digging out Geneva

Slag, concrete, iron dust and tar pits: the long, unglamorous cleanup that turned a dead steel mill into ground people could live on.

The old Geneva land where the new downtown now rises, 2015

The old Geneva land where the new downtown now rises, 2015An Errant Knight, CC BY-SA 4.0, via Wikimedia Commons

A bid for the ground

On a Thursday in November 2005, the last big asset of Geneva Steel went up for sale at a closed auction. It was not a furnace or a rolling mill. Those were already gone, the core steelmaking equipment sold to a Chinese company for $40 million. It was the ground itself, roughly 1,700 acres of it on the shore of Utah Lake.

The winner was Anderson Development LLC, a real estate developer based in Sandy, with a bid of $46.8 million. It beat a rival group backed by Prudential Real Estate Investors. The price came with a catch that would define the next two decades: under the sale agreement, Anderson assumed all responsibility for the remaining demolition and environmental remediation. The land passed to Anderson Geneva, a sister company, and the firm's principal, Gerald Anderson, became the public face of what came next.

For Geneva's creditors it was a rescue. The mill's unsecured creditors, owed about $75 million, had expected 20 to 25 cents on the dollar earlier that year. The sale lifted that to at least 50 cents. "This is a big step forward for the next stage of that site," said James Markus, the bankruptcy trustee.

What the mill left behind

What Anderson bought was not empty land. A Utah steel mill had run here for six decades, and it left behind more than 100 miles of railroad track, more than 100 buildings, foundations, mountains of slag and the chemistry of an integrated mill. Past operations had produced wastes containing arsenic, lead, zinc, nickel, acids, PCBs and petroleum products, and monitoring wells around the perimeter had picked up arsenic, ammonia and benzene in groundwater.

The worst of it was regulated under a state post closure permit that named three closed hazardous waste impoundments: one for acid waste, one for tar decanter sludge and one for miscellaneous waste. United States Steel remained a permittee alongside the new owners, with responsibility divided unit by unit.

Crews finished knocking down the empty mill in 2007. Then came the slower work of taking the ground apart. In 2010, the Pennsylvania company Harsco was hired to process more than a million tons of old blast furnace slag over three years so it could be used in Utah's highway and bridge programs. Much of the slag ended up as road base for the rebuilt Interstate 15 through Utah County.

By August 2012, Stewart Park, Anderson Geneva's project manager, could tick off the numbers. More than 140,000 cubic yards of concrete removed. Forty five thousand tons of scrap metal and 100 tons of copper pulled out and sold. More than 2 million tons of iron fines, the dusty residue of the old process, under contract to be mined and shipped to China to make steel again. Crews were already laying water and sewer lines, storm drains and roads.

Park was emphatic about what the site was not. "This is not a Superfund site," he told KSL. The southern part of the property, the cleanest, had been remediated first to state standards, and that was where most of the planned homes would go. Industrial ground would be cleaned to industrial standards. Redevelopment bonds helped pay for the work on what the Salt Lake Tribune later called one of the largest brownfields west of the Mississippi.

This is not a Superfund site.
Stewart Park, Anderson Geneva, 2012

From @Geneva to a train station

In September 2013, Anderson Development threw an open house to show off the plan, now branded @Geneva. The numbers were enormous for a town that still counted its residents in the hundreds: 7,600 homes, 5 million square feet of industrial space, 3.5 million of offices and 2 million of retail, enough to support 20,000 jobs. The Larry H. Miller Group promised a Megaplex theater with an IMAX screen. Gerald Anderson announced a Day's Market grocery.

By May 2014, Park said the company had spent eight to nine years cleaning the site, and about 60 percent of the land was under contract. Townhomes had sold out. A commuter rail stop, he said, was probably a couple of years away. The first stretch of a new road, the Vineyard Connector, opened in 2014, tying the center of the young city to 800 North and Geneva Road in Orem. The legislature made it State Route 176 in 2017.

The cleanup was not finished, and in the fall of 2019 the neighbors could smell it. For weeks residents of Orem, Lindon and Vineyard complained of a mothball odor strong enough to bring on headaches and nausea. State environmental officials traced it to the coal tar pits on the old mill site, where workers had been moving naphthalene laden waste into engineered landfills elsewhere on the property. Work on that section stopped while air monitors were set up, and officials said the smell posed no health risk.

The rail stop took longer than Park guessed. On August 12, 2022, the Utah Transit Authority opened the Vineyard FrontRunner station at 130 E. Market St., the first new station on the line in a decade, paid for with nearly $17 million from UTA and $5.6 million from the legislature. Governor Spencer Cox came to cut the ribbon in what was by then the fastest-growing city in the state. "We cannot keep adding lanes to I-15," he said.

Utah City

The same day, a new set of developers, The Flagship Cos. and Woodbury Corp., announced an 800 acre district beside the station. In August 2023 it got a new name, Utah City, and a plan built around walking and transit on the old Geneva Steel land. In 2023 UDOT began a $15 million second phase of the Vineyard Connector north toward 1600 North, with an overpass to the station area to follow.

Utah City's developers gave $20 million worth of land for a Huntsman Cancer Institute campus on the old mill ground. It broke ground in April 2025, and on September 1, 2026, builders held a cornerstone ceremony for a 284,000 square foot building where the first patients are expected in 2028. Twenty years after Anderson's bid, the place where Geneva once poured steel is being built for something its founders never imagined: a cancer center, apartments and a train platform by the lake.